Tres Rios Wastewater Reclamation Facility

Complete
Ahead of Schedule
Under Budget
Zero Lost Time
Person icon

client

Pima County Regional Wastewater Reclamation District (RWRD)
Building icon

client type

Municipal
Delivery truck icon

Delivery Method

Construction Manager at Risk (CMAR, CMGC)
Location pinpoint icon

Location

Tuscon
,
AZ
Calendar icon

Start date

May 2008

MWH was the CMAR for this plant expansion that included a 50 million gallons per day (MGD) liquids and solids train replacement. The project also included the construction of a new 37.5mgd, five-stage Bardenpho treatment process by upgrading three 12.5 MGD 3-stage Bardenpho processes and constructing a new 12.5 MGD basin. This project also involved two digesters, a blower building, primary clarifier, two new aeration tanks, five new secondary clarifiers, three new centrifuges, and a new gravity belt thickener building.

MWH managed the preconstruction services, GMP development and general contracting services during construction. In addition, MWH self-performed over 43% of complex aspects of the work to control the critical path, including procurement, installation of process mechanical piping and equipment, six miles of yard piping, instrumentation and control, and commissioning and startup.

MWH created 4D BIM to verify site logistics, yard operations, and temporary facilities. By reviewing the schedule in a rich, visual format, our team made sound decisions based upon multiple sources of accurate real-time information. As the design changed, the model automatically identified the changes and their respective impact on the critical path and overall delivery of the project. MWH used 5D BIM to monitor the project’s construction cost throughout design, rapidly generating an array of essential estimating information including materials quantities and costs, size and area estimates, and productivity projections.

It was imperative that the existing plant remain fully operational. MWH developed more than 450 MOPOs to successfully complete 250 mechanical tie-ins, 350electrical switchover ties, and 3 plant shutdowns without incident. The entire project, including construction and commissioning and startup, was completed while maintaining a fully operational plant.

Project Partners
Jacobs Engineering
McDade Woodcock
Borderland Construction Company
CH2M Hill
Santa Rita Landscaping
Kiewit Infrastructure West Co

"I would like to give my sincere recommendation of the MWH team for completing this work on time and on budget. The project team was responsive to our needs and worked in partnership with our organization to ensure our goals were being met. The resulting product will serve our users well and is a high-quality facility that we are proud of."

Jamie Rivera

Program Manager, Pima County RWRD

Awards

2014 American Public Works Association, Arizona Chapter Public Works Project of the Year
2013 Metropolitan Pima Alliance, Common Ground Award for Partnering

Recent News

Welcome to the New Phoenix Office

After a year of meticulous planning and excited anticipation, MWH’s Phoenix Team moved into their new office on June 1, 2023. Let’s take a look around!

Read More

NTMWD Wylie Water Treatment Plant: Building a More Advanced Filtration System

This $110M Construction Manager-at-Risk (CMAR) project was awarded to MWH by the North Texas Municipal Water District. It consists of four phases and requires the coordination of three separate design teams (Jacobs, Carollo, and HDR).

Read More

How the Biosolids Digester Facilities Project is Setting the new Standards in San Francisco

MWH is continuing to work uninterrupted on the Biosolids Digester Facilities Project (BDFP). The long-term, largescale project represents a significant overhaul of the Southeast Treatment Plant, San Francisco’s largest wastewater pollution treatment plant. BDFP is set to redefine the way wastewater is treated in the city, aiming to process up to 800 million gallons per day (MGD) and serving about 80% of the city’s population. Implementing state-of-the-art technologies and innovation, the project underscores MWH’s commitment to environmental sustainability and urban rejuvenation. The revamped plant will set new standards in waste management and pollution control, marking a major milestone in San Francisco’s environmental management history.

Read More
Back to all Projects